December 6'th\\
Concrete Flooring has poured the Western and Southern grade beams.
A.Urbano has scratched out subgrade for the interior footings of CVS to be poured by CCF on 12/07/05.
Urbano is in the process of leveling under pavement areas to take delivery of light-weight steel framing, plywood, and Dens-Glass on 12/07/05.
Lombardi has backhauled 2/3 of the unusable fill from the CVS excavation.