November 7'th-9'th\\
3/4 of the retail building footings have been poured. VHB was on site Monday to stake out retaining walls and building corners. IMTL is continuing to do compaction tests on all lifts while also inspecting concrete and rebar. CVS will be up to the bottom of footing grade by the end of the day on 11.10.05. Paved areas are also within a few feet of grade around the retail building. Rocks from the CVS excavation have been sized for crushing on 11.10.05.