July 12 '06\\
American Paving has placed the binder course of paving for the entire property.
Nunes Construction has poured all extruded concrete curbing and sidewalks.
A Urbano has demolished the former construction office and begun grading the backside of the property. They have also placed top soil in nearly all islands and landscape areas around the property.
Millwork installers have completed the employee break room, the SOA and most of the displays in CVS. They will be 100% complete by Saturday.
Caplow has completed all bathrooms in CVS and Beacon Electric has installed all hand dryers.
Arnco has placed both CVS/Pharmacy signs.
The drainage swale has been completed per plan and spec and grass has begun to grow within the swale.
North Haven Glass are completing all glass in CVS today and have installed all frames that make up the retail store front.
R&S Roofing has completed flashing on the retail building and will be back tomorrow to finish up CVS.
All framing, rough electrical and plumbing inspections have been conducted in Cingular Wireless and Red Rooster has begun Sheetrocking.
Rennaissance Stucco has completed all EIFS on both buildings.
Beacon Electric has installed the Bird B Gone on CVS...It works!