May 31 '06\\
SBC has placed all new poles on the Post RD.
M Brett Painting has sprayed the first finish coat in CVS. They have also painted the light boxes in the CVS cornice.
A Prime handling has completed the install of the freight lift with the exception of electrical which will be completed tomorrow.
The CVS cooler has been installed completely along with the Roof Top Condendsor.
Red Rooster has framed all demising walls in the Retail building.
Rennaissance Stucco has completed the finish EIFS coat on the back of CVS. They have begun the base coat on the West of CVS.
Dexter has washed and completed all brick work on CVS.
Hop River Concrete has poured the drive thru slabs in CVS.
Massaro has sheetrocked all walls in the retail building and taping is nearly complete. Sheets were left off on two walls for electrical.
Quality Insulation has insulated all demising and perimeter walls in retail.
Central CT Acoustics is near completion of ceiling grid in CVS.
Beacon Electric will have all interior lights installed in CVS by the end of the day. Beacon has installed all seven exterior light poles and all lights in the cornice of CVS.
Savoy Mechanical has begun their drops in CVS.
CCFP have begun running sprinkler lines in retail.
Starbucks has been turned over the to the tenant for fit-up.
A Urbano has completed almost all parking lot grading.
New England Landscaping has planted all trees beneath the retaining wall and placed all sprinkler sleeves in the process.