May 16 '06\\
CL&P has delivered permanent power
Erection and Welding has recieved inspection on the mezzanine stair, roof hatch latter and SOA stairway.
Installation of the CVS cooler has commenced.
Red Rooster has framed and sheethed the Facade of the Retail building. Red Rooster has framed two of the demising walls in retail. Red Rooster is also hanging doors in retail and CVS.
Rennaissance Stucco has completed the finished EIFS coat on the front of CVS. Rain has delayed their progress over the past few days.
Dexter is near completion of final brick washing.
Hop River has poured the slab in retail. They have also formed the Starbucks Drive Thru and the CVS Drive-Thru island.
Bruno Massaro is finish sanding CVS drywall.
Quality Insulation is near completion of perimeter walls of retail.
Savoy Mechanical has run trunk lines to Starbucks.