April 19 '06\\
Red Rooster has framed the bathrooms, bathroom hallway and mezzanine wall in CVS. They are now starting to frame the Soffet above the pharmacy.
Dexter has about 1 1/2 weeks left of Masonry on CVS
Beacon Electric continues to rough in CVS for a projected inspection date of 4/25. Beacon projects to finish a few days ahead of schedule.
A Urbano is beginning to shoot parking grades and lay process..
Rennaissance EIFS has insulated the West wall of the Retail building.
North Haven Glass has set the curtain wall and store front window frames on CVS.