April 14 '06\\
Red Rooster has framed The SOA area in CVS and the Soffet above the large cooler.
Dexter is halfway done with masonry on CVS.
Beacon Electric continues to rough in CVS for a projected inspection date of 4/25.
A Urbano has completed the sanitary sewer system and installation of grease traps.
Beacon Electric and A Urbano have completed the primary electric conduit run from the second transformer to the pole on the Boston Post Rd.