February 27 '06\\
Red Rooster Construction Has installed 60% of the dens glass on CVS. Red Rooster is also near completion of drive thru framing and has framed the cielings in the CVS walkway overhangs.
A Urbano Construction has placed all plastic forms for Guard Rail footings and continues to raise the second retaining wall. They have started to a use a stronger geo-grid towards the top of the wall and have 4.5 courses to go.
Savoy Mechanical has intalled all RTU's on CVS. RTU's will be installed on retail on Friday.
A urbano has installed and backfilled 100' of drainage pipe.