February 21 '06\\
A Urbano has placed the first drainage sump. They also continue to construct the second retaining wall.
Red Rooster has pre-fabricated all of the CVS cornice light boxes and has started to screw them in place. Red Rooster will have the CVS main roof and cornice ready for R&S Roofing by 2/27/06.
VHB has been on site for the last two days to stake all drainage structures, sewer structures, and site poles.