DAILY LOG:
05.16.07//
Utility conduits have been run from pole to 10' from building
All exterior sign and pier footings have been poured.
Stone has been placed and compacted in 1/3 of the building.
Red Rooster's Carpenters have commenced stick framing.
The majority of underground roof leader connections have been run to the storm drainage system.
Sanitary waste has been run and inspected beneath slab.
Domestic water supply has been tapped and run within building.